What Should Buyers Include in an RFQ for a Structural Steel Package?

The short answer

An RFQ for structural steel is more than a request for a price per tonne. Buyers need to define the scope, technical requirements and delivery conditions so that suppliers can prepare quotations on the same basis. Six areas deserve attention: project conditions, technical inputs, scope boundaries, supplier qualifications, bid comparison requirements and evaluation criteria.

If any of these areas is unclear, quotations may cover different requirements, making a direct price comparison unreliable.

Project conditions

State the building’s purpose, site location, applicable design standards, environmental and corrosion exposure, design life and key project dates. Two sheds with similar steel tonnage may require different specifications if one is located in a coastal environment and the other in a dry inland area. The required corrosion protection system can significantly affect the final quotation.

The programme should also identify when the supplier is expected to start and which approvals must be completed before work can proceed.

Technical inputs a fabricator cannot invent

Provide the main span, clear height, design loads, support conditions, cladding interfaces and known penetrations. Relevant loads may include wind, snow, seismic, maintenance and suspended equipment loads, depending on the project location and building use.

For clear height, specify the finished floor level, measurement reference, applicable operating area and the lowest element that must remain clear. Depending on the building’s function, this may include roof members, suspended equipment, cranes, lighting systems or other permanent installations. The required operational clearance should be confirmed before suppliers finalize their designs and quotations.What determines the maximum span follows from the same inputs.

Design responsibility also needs to be clear. The RFQ should identify who establishes the design criteria and load combinations, who performs structural analysis and connection design, who prepares fabrication drawings, and who reviews and approves the submitted documents. Any independent checking or statutory approval requirements should also be stated. Reviewing drawings does not automatically transfer design responsibility to the reviewing party.

Scope boundaries, one line each

List design, detailing, material procurement, fabrication, surface preparation and coating, marking and packing, freight, customs clearance, site erection, testing and handover. Each item should have a clearly assigned responsible party, even when the buyer retains that responsibility.

Two areas often cause disputes. Coating and packing requirements are sometimes described only by reference to general standards, without defining inspection procedures or acceptance criteria. Buyers should specify how coating damage, inadequate protection or packing defects will be assessed.

Coating thickness gauge being read on a finished steel member at the factory

Erection is another important consideration. Whether the roof structure is delivered in prefabricated sections or as individual members affects transportation, lifting equipment, site labour and installation schedules. These requirements should be agreed before quotations are compared.

What a supplier should be asked to submit

Request references from projects with comparable spans, structural systems and environmental conditions, rather than a general list of completed projects.

Ask suppliers to state their fabrication limits, maximum transportable dimensions and weights, and available lifting and handling capacities. These factors, together with shipping restrictions and site erection conditions, influence how the structure is divided into transportable and installable sections.

Other useful documents include quality management procedures, material traceability records and inspection and testing plans. Where welded components are included, specify the applicable welding procedures, welder qualifications and non-destructive testing requirements. The proposed coating system, surface preparation standards and inspection procedures should also be submitted. Where local registration or a local partner is required, identify this early because it may affect supplier eligibility.

Making the bids comparable

Use a common bill of quantities, technical deviation schedule and exclusions list. Require every bidder to follow the same pricing structure and identify any items not included in its offer.

Specify the required delivery arrangement, including the applicable Incoterm, named port or destination, and responsibility for freight, insurance, customs clearance and inland transportation. For site delivery, identify the project location and unloading responsibilities.

The delivery schedule should cover design submission and approval, material procurement, fabrication, inspection, packing and dispatch. Define the contractual starting point and any approvals or payments required before major activities can proceed. Payment terms and bond requirements should also be consistent across bids.

Two suppliers may quote for the same building but include different levels of detailing, connection components, coating protection and packing. Without a common pricing schedule, the lower quotation may simply reflect a narrower supply scope rather than better manufacturing efficiency.

Evaluate compliance before price

First check whether each bid meets the technical requirements and whether responsibilities match the intended scope. Only then compare total delivered costs, including steel, coating, packing, freight, erection support and any clearly identified exclusions.

Comparing price per tonne alone can overlook differences in structural specifications, connection details and delivery scope. A lower initial quotation does not necessarily mean a lower overall project cost.

Where our scope stops

LF-BJMB supplies bolted space frame systems and other steel structures for large-span buildings. Depending on the agreed project scope, the supply package may include structural members, bolted spherical nodes, connection components, secondary framing, purlins and edge members, together with relevant detailing and design documentation. Components are marked and packed according to agreed fabrication, transportation and shipping requirements.

Civil works, foundations, cladding installation, MEP, fire protection and site erection remain outside the supply scope unless otherwise agreed. Our structures are designed for long-term performance under the agreed project conditions. Appropriate inspection and maintenance help preserve their intended service life.

FAQ

Q: We only have a concept design. Can we go to RFQ?

A: Yes, if you issue it as a performance brief covering the main span, clear height, design loads, applicable codes and programme. Ask each bidder to state its assumptions and provide a preliminary cost or tonnage estimate. The technical scope should be reviewed again when the design is sufficiently developed.

Q: Is the lowest price per tonne the cheapest bid?

A: Not necessarily. Compare the delivered cost, technical deviations and assumptions included in each quotation. A lower price may reflect excluded components, different specifications or additional responsibilities left to the buyer.

Conclusion

A well-prepared RFQ gives all bidders the same technical and commercial basis for pricing. It also helps buyers identify differences in scope, responsibilities and delivery conditions before a contract is awarded. The document structure can be reused for future projects, with project-specific requirements updated each time.