According to the characteristics of the project, this project adopts rectangular square pyramid space frame structure with bolt-ball joint.
The National Exhibition and Convention Center has a total construction area of 1.47 million square meters, integrating functions such as exhibitions, conferences, offices, and commercial services.
The National Exhibition and Convention Center has a total construction area of 1.47 million square meters, integrating functions such as exhibitions, conferences, offices, and commercial services.
The building has a construction area of 4188㎡ and an investment of 2 million RMB. The indoor roof structure adopts a bolted ball joint steel roof structure
The building has a construction area of 4188㎡ and an investment of 2 million RMB. The indoor roof structure adopts a bolted ball joint steel roof structure
Limestone pre-homogenization stockpile: 60m×432m, auxiliary material pre-homogenization stockpile: 77m×310m
Limestone pre-homogenization stockpile: 60m×432m, auxiliary material pre-homogenization stockpile: 77m×310m
It features an irregularly shaped steel truss structure, including six connecting corridors, five skylights, four steel roofs, and two cinemas.
It features an irregularly shaped steel truss structure, including six connecting corridors, five skylights, four steel roofs, and two cinemas.
The Olympic Sports Park covers an area of 209,884 square meters, with a total investment of nearly 500 million yuan.
The Olympic Sports Park covers an area of 209,884 square meters, with a total investment of nearly 500 million yuan.
This steel structure project is an airport reconstruction and expansion project. The new passenger terminal building is located on the north side of the existing terminal building.
This steel structure project is an airport reconstruction and expansion project. The new passenger terminal building is located on the north side of the existing terminal building.
Total construction area: 50380m², of which A-2: 24782m², A-3: 25598m². The number of floors of the main body structure is single-story, and the battery warehouse and auxiliary buildings in the workshop are two-story reinforced concrete structures.
Total construction area: 50380m², of which A-2: 24782m², A-3: 25598m². The number of floors of the main body structure is single-story, and the battery warehouse and auxiliary buildings in the workshop are two-story reinforced concrete structures.
The base of the skating hall is elliptical, and the top is streamlined. The building uses smooth aluminum plate lines as the essential elements of the design
The base of the skating hall is elliptical, and the top is streamlined. The building uses smooth aluminum plate lines as the essential elements of the design
The project is divided into three phases with a total construction land area of 81,384.1 square meters.
The project is divided into three phases with a total construction land area of 81,384.1 square meters.