How Should Future Event Loads Be Defined Before an Arena Roof Is Designed?

An arena brief arrives with the seat count, the bowl geometry and the clear span. The event programme arrives much later, sometimes after the roof is in fabrication. By then the numbers that matter to the roof, what will hang from it, where, and how heavy, have been set by assumption rather than by decision.

Event loads are a design input, not a fit-out detail. The owner is the only party who can define them early enough.

The rider is written long after the roof

Every touring production arrives with a technical rider: trusses, hoists, video walls, PA positions, and a weight against each item. A rider is written months before a show; the shows are booked years after the building opens. No owner can predict them one at a time, but an owner can decide the envelope those riders must fit inside.

When that envelope is missing, the venue’s capacity becomes whatever the contractor happened to assume.

What counts as an event load

Part of the load is permanent and known at design: house PA, lighting bars, catwalks, blackout, the scoreboard or video board, and the access equipment reaching them. That set can be scheduled, weighed and drawn.

Part of it cannot. Touring rigging arrives as a plot of hoists; production sets arrive as trusses and drops that move during the show; broadcast adds screens and delay positions. These loads are concentrated and change between events.

The same space also holds roof plant, sprinkler mains, smoke extract and drainage. A roof designed around the permanent set only will be closed to the tours that pay for the building.

Why the code figure does not answer this

Building codes specify relevant roof loads for conditions such as maintenance, snow and wind, but these should not be treated as a substitute for the design loads associated with event rigging.

The structural design must account for the building’s intended use and the actual equipment it is expected to support. Suspended production loads, their attachment locations and applicable load combinations therefore need to be established as part of the project design brief.

Points, not square meters

Rigging loads are applied at specific attachment locations through hooks, clamps or other approved connections. Depending on the structural system, these loads may be transferred through nodes, primary members or designed secondary supports. The load path must be checked rather than assumed.

Useful design information includes the rated capacity at designated rigging points, permitted loading zones, allowable combinations of simultaneous loads and the applicable deflection limits. Deflection matters because changes in roof geometry can affect the alignment and operation of suspended trusses and hoists.

Where loads are applied between nodes or to purlins, the supporting members and connections must be checked for the resulting forces and bending effects. Load distribution through spreader beams or additional support members may be considered where the design requires it.

Bolted spherical node of a space frame roof, with radial members meeting at a single connection point

Four decisions before the drawings freeze

  1. The event mix, and how often each type occurs.

  2. Where productions may hang: over the floor, at the stage end, or not over seating.

  3. What stays permanent and what arrives with each show.

  4. The reserve, and who is allowed to use it.

The documents that carry the decision

A brief does not survive to fabrication on its own. It survives as a small set: a rigging plan showing permitted zones, a node schedule with capacity at every point, the deflection limit and its load case, a rule for penetrations and later equipment, and an as-built record at handover.

Space frame design points for stadiums begin with loads and deflection, before any member size is chosen. The same order applies to an arena, and it is the node schedule that turns the reasoning into something a promoter can use.

Span alone does not determine the structural solution. The feasible span depends on the structural system, geometry, support conditions, material properties, applied loads and serviceability requirements. Defining these conditions early allows the engineer to assess the appropriate structural arrangement before member sizes are finalized.

Who writes it

Owners rarely keep rigging engineers on staff. The work normally falls to a venue technical consultant or a theatre consultant, with the operator and the structural engineer in the room. The engineer cannot invent the intended use; the consultant supplies it, and the two documents have to agree before tender.

Large-span stadium roofs engineered for world-class events are usually specified this way: a technical brief first, a capacity figure afterwards. Reverse the order and the figure becomes a negotiation.

What happens when it is left out

Two outcomes are common. The venue opens with an operating limit that excludes the largest tours, and the roof is strengthened later above a working building. Or the roof carries the load but nobody wrote the number down, so every promoter pays for a structural check before load-in.

Where our scope stops

LF-BJMB supplies long-span steel structures and space frame systems for arena roofs, including design support, structural members, bolt balls and connections, secondary framing, purlins and edge steel. Marking, packing, cladding and erection guidance can be included where the scope specifies them. Where design support is in scope, the node schedule and the deflection limits are issued with the structure. Our frames are engineered for long service life within agreed project parameters, and planned maintenance protects the margins we build in.

Rigging equipment, stage machinery, seating, MEP, fire systems and envelope acoustics stay outside the structural supply.

FAQ

Q: We do not know which shows will come. What do we design for?

A: An envelope, not a list. Fix the maximum point load, the zones where it may be applied, and the deflection limit. Bookings are then tested against those numbers instead of a guess.

Q: Can capacity be added after the venue opens?

A: Locally, sometimes. Across a long span, adding capacity usually means adding structure, and the work happens above an operating venue.

Conclusion

An arena roof is designed twice: for the building, and for the events it will host. Only the first is in the drawings at tender.

Defining the event loads before the roof is detailed costs a workshop and a document set. Leaving them out puts a permanent limit on what the venue can book.